Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You may want to take a look at my mini course on EVA in doc share EVA Forecasting Mini Course before you give this a

You may want to take a look at my mini course on EVA in doc share "EVA Forecasting Mini Course" before you give this a whirl.Project-A Our earned value analysis of Project -A shows us it's a little out of tolerance however given the nature of the project we knew that was likely and within our project contingency reserves. We don't see that situation changing as we complete the effort. While senior management agrees with that assessment they, of course, still want to know what our Estimate at Completion (EAC). Project-B In a similar vein, our earned value analysis of Project -B shows that this project is out of whack as well. The CPI and SPI numbers have been consistently predictive of the effort, but due to a number of circumstances we have not been able to improve them. In addition, this effort has a drop dead date that simply cannot be moved! If we have to do we can move on the budget but the date is set!

EAC

=

AC + Bottom up estimate to completion

Well.. In truth we never really estimated the detailed costs in the first place I reminded the

group. We mostly took the total from the original build multiplied it by an inflation factor and

ALLOCATED the cost downward...

I figured we would get here sooner or later

the boss opined.

What we are saying with THIS

approach is we need to stop and re-estimate all the REMAINING detail tasks, then sum them

up to get a new estimate of future costs and then ADD them to what we have spent so far to

get a brand new EAC.

Probably NOT my best move here. Reminding people

the emperor has no clothes

does NOT make you a popular

guy so I moved rapidly on...

In any case, if this is our best assessment of the facts on the ground

at this point, then Henry needs to get with his people and re-estimate, then get back to us

with his new EAC.

Wait..

Says Henry looking a bit pale.

Didnt you say there was one more approach we

should consider?

Right you are Henry

, the boss and I say simultaneously

(which got a chuckle

from the group which was badly needed about then)

DP George

Page

7

Earned Value

Forecasting

The last one goes like this

(I tell the group)

If we think both the schedule performance and budget

performance are accurately telling us what is happening

, then re-estimation is just going to

confirm that fact and waste more time, money, and effort to add to the problem. If we cant

move the completion date (and we can all agree that is something we REALLY need to avoid)

then we can use what we know to be case (our current efficiencies) and project them through

until the end). If we do that then

our EAC is calculated as:

EAC

=

AC + {(BAC - EV)/(CPI x SPI)}

You left out the phases of the moon! Mike spat out from the back of the room. That looks like

alphabet soup! Look I manage a production operation Im not a statistician!

I knew Mike couldnt

stay quiet forever

, I told him ---

Wait Mike, let me explain this formula. You guys can follow this

stuff just fine! We just need to take it one step at a time.

First of all we have AC. T

hat

is just our actual costs to date in the project right? Right!

To that we add our budget adjusted for how much we have used up for the progress we have

made so far. That is just BAC EV as we have seen in earlier versions of EAC calculations.

Yes?!

But if we JUST did that we would NOT have adjusted from our original budget assumptions to

what we are finding on the ground in terms of budget expense and schedule progress. To do

THAT we need to adjust the (BAC EV) by how efficient we our with our budget AND our

schedule which is the product of CPI and SPI

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Commodity Market Trading And Investment

Authors: Tom James

1st Edition

1137432802, 978-1137432803

More Books

Students also viewed these Finance questions