Answered step by step
Verified Expert Solution
Question
1 Approved Answer
You pay a consultant $1000/day. The task will take 3 days, therefore the cost of this task is $3000. This is an example of which
You pay a consultant $1000/day. The task will take 3 days, therefore the cost of this task is $3000. This is an example of which cost estimating technique Parametric
Three-point
Reserve
Bottom-up