Question
You will need to re-draw the following network diagram (or complete the blank one posted in Stream) and complete the forward and backward passes to
You will need to re-draw the following network diagram (or complete the blank one posted in Stream) and complete the forward and backward passes to do this.
Marks available indicated below. No need to upload anything, just select your responses for the lists on screen.
Activity | TE |
---|---|
A | 3 |
B | 5 |
C | 6 |
D | 6 |
E | 8 |
F | 5 |
G | 8 |
H | 4 |
I | 7 |
J | 20 |
K | 5 |
L | 8 |
M | 7 |
N | 5 |
O | 8 |
What is the critical path?
What is the full length of the project?
What is the early start (ES) for activity F?
What is the early finish (EF) for activity F?
What is the late start (LS) for activity G?
What is the late finish (LF) for activity G?
What is the early start (ES) for activity J?
What is the early finish (EF) for activity J?
What is the late start (LS) for activity K?
What is the late finish (LF) for activity K?
What is the float (or slack) for activity J?
What is the float (or slack) for activity M?
What kind of activity is activity A?
What kind of activity is activity N?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started