You work for a company that produces customized gift baskets. A recent order consisted of 60 baskets to be completed in 4 days. The total

You work for a company that produces customized gift baskets. A recent order consisted of 60 baskets to be completed in 4 days. The total cost of the project is $480.

By the end of Day 3, this is the situation:

  • 48 baskets have been completed
  • Incurred a cost of $432

What is the Planned Value at the end of Day 3?

Question 1 options:

45 x $8 per invitation = $360

40 x $6 per invitation = $240

48 x $8 per invitation = $384

Question 2 (1 point)

Saved

ListenReadSpeaker webReader: Listen

You work for a company that produces customized gift baskets. A recent order consisted of 60 baskets to be completed in 4 days. The total cost of the project is $480.

By the end of Day 3, this is the situation:

  • 48 baskets have been completed
  • Incurred a cost of $432

What is the EarnedValue at the end of Day 3?

Question 2 options:

48 x $8 per invitation = $384

40 x $6 per invitation = $240

60 x $8 per invitation = $480

Question 3 (1 point)

Saved

ListenReadSpeaker webReader: Listen

You work for a company that produces customized gift baskets. A recent order consisted of 60 baskets to be completed in 4 days. The total cost of the project is $480.

By the end of Day 3, this is the situation:

  • 48 baskets have been completed
  • Incurred a cost of $432

What is the Actual Cost at the end of Day 3?

Question 3 options:

$384

$480

$432

Question 4 (1 point)

Saved

ListenReadSpeaker webReader: Listen

Choose the correct formula and calculations for the ScheduleVarianceof this project.

Question 4 options:

Schedule Variance= PV-EV = $360 - $432 = $312

Schedule Variance= EV-PV = $384 - $360 = $24

Schedule Variance= EV-AC = $384 - $432 = - $48

Question 5 (1 point)

Saved

ListenReadSpeaker webReader: Listen

Choose the correct formula and calculations for the CostVarianceof this project.

Question 5 options:

Cost Variance= EV-PV = $384 - $360 = $24

Cost Variance= EV-AC = $384 - $432 = - $48

Cost Variance= PV-EV = $360 - $432 = $312

Question 6 (1 point)

Saved

ListenReadSpeaker webReader: Listen

Using the information that you have gained from your calculations, would you say that currently the project is behind or ahead of schedule?

Question 6 options:

The project is ahead of schedule

The project is behind schedule

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions

Question

What is operatiing system?

Answered: 1 week ago