Your 12-month project has a total cost of $200K. After three months, you've spent $70K. The project was slated to be 25% done but is
Your 12-month project has a total cost of $200K. After three months, you've spent $70K. The project was slated to be 25% done but is only 20% done. What's the earned value (EV) of the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
The Earned Value EV of the project is 50 000 Heres how we can calculate it Planned Budget for the Pe...Get Instant Access to Expert-Tailored Solutions