Your client will give you a $1750 bonus if you can crash the schedule to 13 weeks. Act Imm (Normal) Crash Normal Crash ACT Pred
Your client will give you a $1750 bonus if you can crash the schedule to 13 weeks.
Act | |||||
| Imm | (Normal) | Crash | Normal | Crash |
ACT | Pred | Time | Time | Cost | Cost |
A | - | 6 | 5 | 1000 | 1700 |
B | - | 8 | 6 | 300 | 600 |
C | - | 4 | 2 | 400 | 1200 |
D | A | 6 | 4 | 500 | 1500 |
E | B,D | 2 | 1 | 300 | 600 |
F | B | 3 | 2 | 500 | 700 |
G | F | 1 | 1 | 150 | 150 |
H | G | 1 | 1 | 600 | 600 |
|
|
|
|
|
|
What is the original length (before crashing) of the Critical Path?
What is the cost to crash to 13 weeks?
Do you recommend crashing and collecting bonus?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started