Your company is planning to initiate the construction of a commercial project. As a technician, you have been tasked to estimate the project's time. Calculate
Your company is planning to initiate the construction of a commercial project. As a technician, you have been tasked to estimate the project's time. Calculate the estimated time using the three-point estimating method by considering the information given when: a. equally distributed in weight or giving more weight as listed below. b. Giving more weight, or importance, in the most likely. Most likely: 90 days Optimistic: 85 days Pessimistic: 117 days