Question

1 Approved Answer

Your company Portfolio Manager is convening a review board in the first calendar quarter to consider three mutually exclusive projects. You have been asked to

Your company Portfolio Manager is convening a review board in the first calendar quarter to consider three mutually exclusive projects. You have been asked to provide recommendations with respect to the capital budgeting aspects of these projects. Your recommendations will be considered by the review board along with other non-financial aspects of the projects. Initial (year 0) funding will be provided in the current year for the single project selected. Note: The review board may select a project for strategic reasons even if the financial aspects are not ideal.

Project sponsors have provided the following estimated cash flow projections:

The company has not yet decided how the selected project will be financed. The cost of capital or hurdle rate will vary depending upon how the company decides to finance the project.

You decide to compare projects in three areas:

(1) payback period (not considering the cost of capital);

(2) NPV sensitivity (see note 1 below); and (3) Internal Rate of Return (IRR). Conduct each analysis and interpret the results.

You must make as complete a recommendation as possible so that the board understands the financial implications of whatever decision they make. Based on your analysis, what would you recommend to the review board and why? Your recommendation must be based on the combination of all three factors (payback period, IRR, and NPV sensitivity).

Show all calculations supporting your recommendation. Calculate NPV to the nearest dollar, IRR to three decimal places, and payback period to one decimal place.

For uniformity, please use 5%, 10% & 15% as the 3 discount rates.

Note 1: Project NPV varies inversely with the cost of funds to perform the project (expressed as the hurdle rate or kin the NPV discount factor formula). Some project NPVs are more sensitive to changes in k than others. See the NPV Profile discussion in Gallagher, Chapter 10, pages 278-279 (Reserved Readings) for information on determining NPV sensitivity

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions

Question

Question In Chemical Engineering, Don't Give AI Answer 2 8 .

Answered: 1 week ago

Question

1. What is Ebola ? 2.Heart is a muscle? 3. Artificial lighting?

Answered: 1 week ago