Answered step by step
Verified Expert Solution
Link Copied!

Question

...
1 Approved Answer

Your Contracting team has awarded a Cost-plus Fixed Fee Low Cost Technically Acceptable Level of Effort Contract to a small business for the research development

Your Contracting team has awarded a Cost-plus Fixed Fee Low Cost Technically Acceptable Level of Effort Contract to a small business for the research development and build of a working prototype screen which will be incorporated into virtual reality heads up display unit for Special Operations. The Contract was awarded using a Low Cost Technically Acceptable evaluation method and was synopsized as a total small business set aside in order to meet your organizations small business contracting goals and objectives, even though your market research indicated that there we no small business capable of developing and producing this item. The contractor is six months behind schedule and has expended 75% of the total funds but has only completed 45% of the development work. The contract is divided up into main sections. The first is the design of the system and the second part is to build a prototype. The

program office is saying that there may not be enough funding in their budget to pay for the all the contractors' cost overruns. This screen is critical for the next phase of the heads-up display unit and will be incorporated into another system which is being built by another company. This delay and cost overrun is going to hold up other phases of the program. Your SES wants to terminate this contractor for default, but your Commanding General wants to continue with the program. The contractor claims that the work is too complicated and that they were given technical specifications that were ambiguous as well direction from the General that were incorrect on how to proceed with the program, which has caused them to fall behind schedule and have a cost overrun. Now it is your job to come up with a solution on how to resolve and or mitigate this issue. What are your Options and how would you implement these options contractually? Also, the General and your SES want this to be a teachable moment and they are asking your team to develop new policies, procedures, and guidelines on how to

resolve or mitigate this issue and to prevent this happening in the first place.

In several brief paragraphs, Compare and contrast how termination for convenience (t4c) and termination for default (t4d) would be beneficial based off of THIS scenario. Throughout the paragraphs, discuss the "costs" of each.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting for Governmental and Nonprofit Entities

Authors: Earl R. Wilson, Jacqueline L Reck, Susan C Kattelus

16th Edition

978-0078110931

Students also viewed these General Management questions