Your initial plan was to finish all configuration work before testing would start.However, due to some delays, you have decided to start testing even though
Your initial plan was to finish all configuration work before testing would start.However, due to some delays, you have decided to start testing even though configuration isnot yet complete. Which of the following would best describe this situation?
A) You have changed a start to finish relationship to a finish to start relationship.
B) You have changed a finish to start to a start to start relationship.
C) You have changed a mandatory dependency to a discretionary dependency.
D) You have changed soft logic to hard logic.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started