Your organization has provided a rough order of magnitude estimation for the resources on the project. Based on what you know about cost estimation techniques,
Your organization has provided a rough order of magnitude estimation for the resources on the project. Based on what you know about cost estimation techniques, what stage of the project life cycle do you believe the organization is in?
a.
The project is in the execution phase.
b.
The project is in the concept phase.
c.
The project is in the termination phase.
d.
The project is in the development phase.