Your project is running behind schedule, but you have plenty of float on some activities. You decide to move resources from noncritical path activities to
Your project is running behind schedule, but you have plenty of float on some activities. You decide to move resources from noncritical path activities to critical path activities. What are you performing?
A) Resource leveling
B) Crashing
C) Resource smoothing
D) Fast tracking