Your project is to construct a new technology museum at Fanshawe College. The cost baseline shows costs of $2,500 each day, for the 100 day
Your project is to construct a new "technology museum" at Fanshawe College. The cost baseline shows costs of $2,500 each day, for the 100 day duration of the $250,000 project. It is now Day 50. The SPI= 0.80, and CPI = 0.9. What is the approximate AC? There is not enough information to determine AC. $90,000
$100,000
$110,000
$125,000