Your project to obtain charitable donations is now 4 4 days into a planned 5 4 - day project. The project is divided into 3
Your project to obtain charitable donations is now days into a planned day project. The project is divided into activities. The first activity is designed to solicit individual donations. It is scheduled to run the first days of the project and to bring in $ Even though we are days into the project, we still see that we have only percent of this activity complete. The second activity relates to company donations and is scheduled to run for days starting on day and extending through day We estimate that, even though we should have : percent of this activity complete, it is actually only percent complete. This part of the project was scheduled to bring in $ in donations. The final activity is for matching funds. This activity is scheduled to run the last days of the project and has not started. It is scheduled to bring in an additional $ So far $ has actually been brought in on the project.
Calculate the schedule variance, schedule performance index, cost variance, and cost actually value in this case performance index.
Note: Negative values should be indicated by a minus sign. Do not round intermediate calculations. Round your dollar amounts to the nearest whole number. Round your "performance index" values to decimal places.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started