Your TCT 2 is still higher than the Takt time. Your project team decides to invest in another production machine to further reduce the TCT.

Your TCT2 is still higher than the Takt time. Your project team decides to invest in another production machine to further reduce the TCT. Calculate the new TCT3 based on 2 production machines and the recently improved setup time ST2.

ROUND 3 TOTAL CYCLE TIME PER UNIT WITH 2 MACHINES
New number of machines MC3 (given):MC3 = _____

New total cycle time in minutes per unit:

image text in transcribed
\f

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Working In Teams Moving From High Potential To High Performance

Authors: Brian A. Griffith ,Ethan B. Dunham

1st Edition

1452286302, 978-1452286303

More Books

Students also viewed these General Management questions