Question

1 Approved Answer

Your team has demonstrated three product increments, but the stakeholders have been disappointed each time. Which of the following recommendations would not improve the quality

Your team has demonstrated three product increments, but the stakeholders have been disappointed each time. Which of the following recommendations would not improve the quality of the product increments being delivered?

Select one:

a. Change to a pure agile approach, and stop writing requirements.

b. The requirements should be reviewed and approved before coding.

c. The team should prototype a solution to get feedback before finalizing it.

d. Revisit the project charter to confirm the objectives of the project.

Question 30

On an agile project, who is responsible for ensuring the quality of the end product?

Select one:

a. The development team should verify, validate, and test the product while it is being built.

b. The users should try out the first release and send feedback and bug reports to the team.

c. The project manager should check the quality of the product before release.

d. The customer should review the product as it is built to ensure that it is fit for business purpose.

8

Question 28

As the project manager, what can you do to support your agile team's efforts to improve quality?

Select one:

a. Carefully follow their progress, and assign improvement initiatives at the iteration retrospectives.

b. Investigate and try to quickly resolve any impediments mentioned in the team's daily standup.

c. Monitor their work to ensure that the development cycle time doesn't fall too rapidly.

d. Leave the team alone as much as possible to allow them to build their problem-solving skills.

omework

Q 27

Question 27

You've been asked to explain the concept of an agile retrospective meeting to a stakeholder who has never worked with an agile team before. You say, "It's a meeting where we __________."

Select one:

a. discuss what will be delivered in the next iteration and how that work will be achieved

b. refine and update the product backlog, based on input from the product owner

c. reflect on what happened in the last iteration, gather lessons learned, and look for improvements

d. show the product owner the product increment we've just built, and get feedback

11

Question 11

A project manager is working with quality professionals in the Perform Quality Assurance process of the project. Which of the following activities is being performed?

Select one:

a. Performing quality control

b. Evaluating quality against the processes

c. Determining what processes should be used

d. Determining if the right processes are being used

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these General Management questions

Question

What is liquidity? Identify one measure of liquidity.

Answered: 1 week ago