Question
1 Approved Answer
You're managing a project using the earned value for cost management. The project planned value ( PV ) is $ 2 0 0 , 0
You're managing a project using the earned value for cost management. The project planned value PV is $ The project earned value EV is $ The actual value AV is $ Calculate the cost performance index CPI for the project.