You've estimated the following cash flows (in $) for a project: A B 1 Year Cash flow 2 0 -3,430 3 1 974 4 2
You've estimated the following cash flows (in $) for a project:
A | B | |
1 | Year | Cash flow |
2 | 0 | -3,430 |
3 | 1 | 974 |
4 | 2 | 1,281 |
5 | 3 | 1,996 |
The required return is 8.5%.
1. What is the IRR for the project?
2. What is the NPV of the project?
3 .What should you do?
Check all that apply:
Reject the project based on its NPV
Reject the project based on its IRR
Accept the project based on its IRR
Accept the project based on its NPV