Question
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver
Engineering design $120,000 Engineering Hours 3,000 hrs
Purchasing 80,000 Number of parts 10,000 parts
Other overhead 250,000 Direct labor hours 40,000 hours
Zayner worked on five jobs in July. Data are as follows:
Job #60 Job # 61 Job # 62 Job # 63 Job # 64
Balance, 7/1 $32,450 $40,770 $29,090 $0 $0
Direct materials $26,000 $37,900 $25,350 $11,000 $13,560
Direct labor $40,000 $38,500 $43,000 $20,900 $18,000
Engineering hours 20 10 15 100 200
Number of parts 150 180 200 500 300
Direct labor hours 2,500 2,400 2,600 1,200 1,100
By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver
Engineering design $120,000 Engineering Hours 3,000 hrs
Purchasing 80,000 Number of parts 10,000 parts
Other overhead 250,000 Direct labor hours 40,000 hours
Zayner worked on five jobs in July. Data are as follows:
Job #60 Job # 61 Job # 62 Job # 63 Job # 64
Balance, 7/1 $32,450 $40,770 $29,090 $0 $0
DireZayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver
Engineering design $120,000 Engineering Hours 3,000 hrs
Purchasing 80,000 Number of parts 10,000 parts
OtheZayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:
Activity Cost Driver Amount of Driver
Engineering design $120,000 Engineering Hours 3,000 hrs
Purchasing 80,000 Number of parts 10,000 parts
Other overhead 250,000 Direct labor hours 40,000 hours
Zayner worked on five jobs in July. Data are as follows:
Job #60 Job # 61 Job # 62 Job # 63 Job # 64
Balance, 7/1 $32,450 $40,770 $29,090 $0 $0
Direct materials $26,000 $37,900 $25,350 $11,000 $13,560
Direct labor $40,000 $38,500 $43,000 $20,900 $18,000
Engineering hours 20 10 15 100 200
Number of parts 150 180 200 500 300
Direct labor hours 2,500 2,400 2,600 1,200 1,100
By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.
Required:
1. Calculate the activity rates for each of the three overhead activities.
2. Prepare job-order cost sheets for each job showing all costs through July 31.
3. What is the cost of each job by the end of July?
r overhead 250,000 Direct labor hours 40,000 hours
Zayner worked on five jobs in July. Data are as follows:
Job #60 Job # 61 Job # 62 Job # 63 Job # 64
Balance, 7/1 $32,450 $40,770 $29,090 $0 $0
Direct materials $26,000 $37,900 $25,350 $11,000 $13,560
Direct labor $40,000 $38,500 $43,000 $20,900 $18,000
Engineering hours 20 10 15 100 200
Number of parts 150 180 200 500 300
Direct labor hours 2,500 2,400 2,600 1,200 1,100
By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.
Required:
1. Calculate the activity rates for each of the three overhead activities.
2. Prepare job-order cost sheets for each job showing all costs through July 31.
3. What is the cost of each job by the end of July?
ct materials $26,000 $37,900 $25,350 $11,000 $13,560
Direct labor $40,000 $38,500 $43,000 $20,900 $18,000
Engineering hours 20 10 15 100 200
Number of parts 150 180 200 500 300
Direct labor hours 2,500 2,400 2,600 1,200 1,100
By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.
Required:
1. Calculate the activity rates for each of the three overhead activities.
2. Prepare job-order cost sheets for each job showing all costs through July 31.
3. What is the cost of each job by the end of July?
Required:
1. Calculate the activity rates for each of the three overhead activities.
2. Prepare job-order cost sheets for each job showing all costs through July 31.
3. What is the cost of each job by the end of July?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started