Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related

Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver

Engineering design $120,000 Engineering Hours 3,000 hrs

Purchasing 80,000 Number of parts 10,000 parts

Other overhead 250,000 Direct labor hours 40,000 hours

Zayner worked on five jobs in July. Data are as follows:

Job #60 Job # 61 Job # 62 Job # 63 Job # 64

Balance, 7/1 $32,450 $40,770 $29,090 $0 $0

Direct materials $26,000 $37,900 $25,350 $11,000 $13,560

Direct labor $40,000 $38,500 $43,000 $20,900 $18,000

Engineering hours 20 10 15 100 200

Number of parts 150 180 200 500 300

Direct labor hours 2,500 2,400 2,600 1,200 1,100

By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.

Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver

Engineering design $120,000 Engineering Hours 3,000 hrs

Purchasing 80,000 Number of parts 10,000 parts

Other overhead 250,000 Direct labor hours 40,000 hours

Zayner worked on five jobs in July. Data are as follows:

Job #60 Job # 61 Job # 62 Job # 63 Job # 64

Balance, 7/1 $32,450 $40,770 $29,090 $0 $0

DireZayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver

Engineering design $120,000 Engineering Hours 3,000 hrs

Purchasing 80,000 Number of parts 10,000 parts

OtheZayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver

Engineering design $120,000 Engineering Hours 3,000 hrs

Purchasing 80,000 Number of parts 10,000 parts

Other overhead 250,000 Direct labor hours 40,000 hours

Zayner worked on five jobs in July. Data are as follows:

Job #60 Job # 61 Job # 62 Job # 63 Job # 64

Balance, 7/1 $32,450 $40,770 $29,090 $0 $0

Direct materials $26,000 $37,900 $25,350 $11,000 $13,560

Direct labor $40,000 $38,500 $43,000 $20,900 $18,000

Engineering hours 20 10 15 100 200

Number of parts 150 180 200 500 300

Direct labor hours 2,500 2,400 2,600 1,200 1,100

By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.

Required:

1. Calculate the activity rates for each of the three overhead activities.

2. Prepare job-order cost sheets for each job showing all costs through July 31.

3. What is the cost of each job by the end of July?

r overhead 250,000 Direct labor hours 40,000 hours

Zayner worked on five jobs in July. Data are as follows:

Job #60 Job # 61 Job # 62 Job # 63 Job # 64

Balance, 7/1 $32,450 $40,770 $29,090 $0 $0

Direct materials $26,000 $37,900 $25,350 $11,000 $13,560

Direct labor $40,000 $38,500 $43,000 $20,900 $18,000

Engineering hours 20 10 15 100 200

Number of parts 150 180 200 500 300

Direct labor hours 2,500 2,400 2,600 1,200 1,100

By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.

Required:

1. Calculate the activity rates for each of the three overhead activities.

2. Prepare job-order cost sheets for each job showing all costs through July 31.

3. What is the cost of each job by the end of July?

ct materials $26,000 $37,900 $25,350 $11,000 $13,560

Direct labor $40,000 $38,500 $43,000 $20,900 $18,000

Engineering hours 20 10 15 100 200

Number of parts 150 180 200 500 300

Direct labor hours 2,500 2,400 2,600 1,200 1,100

By July 31, Jobs #60, and # 62 were completed and sold. The remaining jobs were in process.

Required:

1. Calculate the activity rates for each of the three overhead activities.

2. Prepare job-order cost sheets for each job showing all costs through July 31.

3. What is the cost of each job by the end of July?

Required:

1. Calculate the activity rates for each of the three overhead activities.

2. Prepare job-order cost sheets for each job showing all costs through July 31.

3. What is the cost of each job by the end of July?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Connect For Payroll Accounting 2020

Authors: Jeanette Landin

6th Edition

1260943895, 9781260943894

More Books

Students also viewed these Accounting questions

Question

What causes a partnership to dissolve?

Answered: 1 week ago