Zero-base budgeting requires Group of answer choices accounting for the receipt and timing of all sources and expenditures of cash. a review of all activities
Zero-base budgeting requires Group of answer choices accounting for the receipt and timing of all sources and expenditures of cash. a review of all activities and related costs of an event as if it were the first time. informing the manager of the cash amount needed to pay expenses at predetermined times. usage of last year's budget with only minor changes being allowed