2. The elapsed time for delivery of the hardware is esti- mated at 90 days. Would the...

Question:

2. The elapsed time for delivery of the hardware is esti- mated at 90 days. Would the project completion time be affected if delivery of the hardware were delayed by 30 days? Would the critical path change?