Crash the completion time to the minimum level. Activity Normal Time, Weeks Cost Crash Time, Weeks Cost
Question:
Crash the completion time to the minimum level.
Activity Normal Time, Weeks Cost Crash Time, Weeks Cost A 4 $2,500 2 $6,000 B 5 4,000 4 5,000 C 2 3,000 1 5,000 D 2 2,000 1 3,000 E 6 3,000 4 4,000 F 3 2,000 1 5,000 G 1 2,000 1 2,000 A
C B D End E
C A
Start B
D G F
End 398 Part Three Managing Service Operations