23.6. Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback

Question:

23.6. Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback occurs and instead of taking 10 days, task T5 takes 40 days. Draw up new bar charts showing how the project might be reorganized.