=+23.6. Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback

Question:

=+23.6. Figure 23.14 shows the task durations for software project activities. Assume that a serious, unanticipated setback occurs, and instead of taking 10 days, task T5 takes 40 days. Draw up new bar charts showing how the project might be reorganized.

Step by Step Answer:

Related Book For  book-img-for-question

Software Engineering

ISBN: 9780133943030

10th Edition

Authors: Ian Sommerville

Question Posted: