=+34.6. The relationship between people and time is highly nonlinear. Using Putnam's soft- ware equation (described in
Question:
=+34.6. The relationship between people and time is highly nonlinear. Using Putnam's soft-
ware equation (described in Section 34.2.2), develop a table that relates number of people to project duration for a software project requiring 50,000 LOC and 15 person-years of effort
(the productivity parameter is 5000 and B = 0.37). Assume that the software must be deliv-
ered in 24 months plus or minus 12 months.