Fill in the blank: Once a process has been brought into a state of statistical control, i.

Question:

Fill in the blank: Once a process has been brought into a state of statistical control,

i. It must still be monitored continually.

ii. Monitoring can be stopped for a while, since it is unlikely that the process will go out of control again right away.

iii. The process need not be monitored again, unless it is redesigned.