10. Which of the following is not the normal reason for a change in a lump-sum or...

Question:

10. Which of the following is not the normal reason for a change in a lump-sum or fixed price contract?

a. Differing site or unforeseen conditions.

b. Delays caused by contractor inactivity

c. An increase or decrease in owner requirements

d. An error in the design documents