A supplier of instrument gauge clusters uses a kanban system to control material flow. The gauge cluster
Question:
A supplier of instrument gauge clusters uses a kanban system to control material flow. The gauge cluster housings are transported five at a time. A fabrication center produces approximately 10 gauges per hour. It takes approximately two hours for the housing to be replenished. Due to variations in processing times, management has decided to keep 20 percent of the needed inventory as safety stock.
How many kanban card sets are needed? (Answer in Appendix E)
LO14-4
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
ISE Operations And Supply Chain Management
ISBN: 9781260575941
16th International Edition
Authors: F. Robert Jacobs, Richard B. Chase
Question Posted: