Jobs A, B, C, D, and E must go through Processes I and II in that sequence

Question:

Jobs A, B, C, D, and E must go through Processes I and II in that sequence (Process I first, then Process II). Use Johnson’s rule to determine the optimal sequence in which to schedule the jobs to minimize the total required time.

Job Required Processing Time on I Required Processing Time on II A 4 5 B 16 14 C 8 7 D 12 11 E 3 9 WT-202