Joe is the production scheduler in a brand-new custom refinishing auto service shop located near the border.
Question:
Joe is the production scheduler in a brand-new custom refinishing auto service shop located near the border. This system is capable of handling 10 cars per day. The sequence is customizing first, followed by repainting.
Car Customizing Time
(hours)
Painting
(hours) Car Customizing Time
(hours)
Painting
(hours)
1 3.0 1.2 6 2.1 0.8 2 2.0 0.9 7 3.2 1.4 3 2.5 1.3 8 0.6 1.8 4 0.7 0.5 9 1.1 1.5 Customizing Time (hours)
Painting (hours) Car Customizing Time (hours)
Painting (hours)
5 1.6 1.7 10 1.8 0.7 In what sequence should Joe schedule the cars to minimize the time needed to complete all the cars?WT-202
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
ISE Operations And Supply Chain Management
ISBN: 9781260575941
16th International Edition
Authors: F. Robert Jacobs, Richard B. Chase
Question Posted: