Lambda Computer Products competed for and won a contract to produce two prototype units of a new

Question:

Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits.

The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 3,500 hours and used $200,000 worth of materials, equipment usage, and supplies. Labor is $30 per hour.

The company expects “learning” to occur relative to labor and also the pricing of parts from suppliers.

a. Lambda was asked to present a bid for 10 additional units as soon as the second unit was completed. Production would start immediately. What would this bid be?

b. Suppose there was a significant delay between the contracts.

During this time, personnel and equipment were reassigned to other projects. Explain how this would affect the subsequent bid.

LO-1

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

ISE Operations And Supply Chain Management

ISBN: 9781260575941

16th International Edition

Authors: F. Robert Jacobs, Richard B. Chase

Question Posted: