The following table contains information regarding jobs that are to be scheduled through one machine: Job Processing
Question:
The following table contains information regarding jobs that are to be scheduled through one machine:
Job Processing Time Due Date A 4 20 B 12 30 C 2 15 D 11 16 E 10 18 F 3 5 G 6 9
a. What is the first-come, first-served (FCFS) schedule?
b. What is the shortest operating time (SOT) schedule?
c. What is the slack time remaining (STR) schedule?
d. What is the earliest due date (EDD) schedule?
e. What are the mean flow times for each of the schedules above?WT-202