A manufacturing facility has five jobs to be scheduled into production. The following table gives the processing

Question:

A manufacturing facility has five jobs to be scheduled into production. The following table gives the processing times plus the necessary wait times and other necessary delays for each of the jobs. Assume that today is April 3, that the facility will work every day between now and the due dates, and the jobs are due on the dates shown:

Days of Actual Processing Time Required Days of Necessary Delay Time Total Time Required Date Job Due 1 2 12 14 April 30 2 5 8 13 April 21 3 9 15 24 April 28 4 7 9 16 April 29 5 4 22 26 April 27 Determine two schedules, stating the order in which the jobs are to be done. Use the critical ratio priority rule for one. You may use any other rule for the second schedule as long as you state what it is.
(Answer in Appendix E)WT-202

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

ISE Operations And Supply Chain Management

ISBN: 9781260575941

16th International Edition

Authors: F. Robert Jacobs, Richard B. Chase

Question Posted: