The following list of jobs in a critical department includes estimates of their required times: Job Required

Question:

The following list of jobs in a critical department includes estimates of their required times:

Job Required T (days) Days to Delivery Promise Slack A 8 12 4 B 3 9 6 C 7 8 1 D 1 11 10 E 10 −10 (late) −20 F 6 10 4 G 5 −8 (late) −13 H 4 6 2

a. Use the shortest operation time rule to schedule these jobs.

What is the schedule?

What is the mean flow time?

b. The boss does not like the schedule in part (a). Jobs E and G must be done first, for obvious reasons. (They are already late.)

Reschedule and do the best you can while scheduling Jobs E and G first and second, respectively.

What is the new schedule?

What is the new mean flow time?

WT-202

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

ISE Operations And Supply Chain Management

ISBN: 9781260575941

16th International Edition

Authors: F. Robert Jacobs, Richard B. Chase

Question Posted: