There is an 82 percent chance the following project can be completed in X weeks or less.
Question:
There is an 82 percent chance the following project can be completed in X weeks or less. What is X?
Activity Most Optimistic Most Likely Most Pessimistic A 2 5 11 B 3 3 3 C 1 3 5 D 6 8 10 E 4 7 10LO5-1