The following represents a project that should be scheduled using CPM: Times (days) Activity Immediate Predecessors a
Question:
The following represents a project that should be scheduled using CPM:
Times (days)
Activity Immediate Predecessors a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5
a. Draw the network.
b. What is the critical path?
c. What is the expected project completion time?
d. What is the probability of completing this project within 16 days?
LO5-1
Step by Step Answer:
Related Book For
ISE Operations And Supply Chain Management
ISBN: 9781260575941
16th International Edition
Authors: F. Robert Jacobs, Richard B. Chase