The following represents a project that should be scheduled using CPM: Times (days) Activity Immediate Predecessors a

Question:

The following represents a project that should be scheduled using CPM:

Times (days)

Activity Immediate Predecessors a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5

a. Draw the network.

b. What is the critical path?

c. What is the expected project completion time?

d. What is the probability of completing this project within 16 days?