2 What steps will the supplier need to take in order to satisfy call-off orders from WestCo?...

Question:

2 What steps will the supplier need to take in order to satisfy call-off orders from WestCo? A problem that is all too familiar to suppliers in the automotive industry is that of schedule variability. A vehicle manufacturer issues delivery schedules to specify how many parts of each type are required each day for the following month. And each day a ‘calloff’

quantity is issued, which specifies how many the vehicle manufacturer actually wants. The two sets of figures are not necessarily the same, although they usually add up to the same cumulative numbers for the month as a whole. In other words, the total scheduled quantities and the total call-off quantities are the same. So what is the problem?