1. Excelsior Springs Ltd. schedules production of one end product, Hi-
Sulphur, in batches of 80 units whenever the projected ending inventory balance in a quarter falls below 10 units. It takes one quarter to make a batch of 80 units. Excelsior currently has 30 units on hand. The forecast for the next four quarters is:
a. Prepare a time-phased MPS record showing the forecast and MPS for Hi-Sulphur.
b. What are the inventory balances at the end of each quarter?
c. During the first quarter, no units were sold. The revised forecast for the rest of the year is:
How does the MPS change?