1. Excelsior Springs Ltd. schedules production of one end product, Hi- Sulphur, in batches of 80 units...

Question:

1. Excelsior Springs Ltd. schedules production of one end product, Hi-

Sulphur, in batches of 80 units whenever the projected ending inventory balance in a quarter falls below 10 units. It takes one quarter to make a batch of 80 units. Excelsior currently has 30 units on hand. The forecast for the next four quarters is:

image text in transcribed

a. Prepare a time-phased MPS record showing the forecast and MPS for Hi-Sulphur.

b. What are the inventory balances at the end of each quarter?

c. During the first quarter, no units were sold. The revised forecast for the rest of the year is:

image text in transcribed

How does the MPS change?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: