14. Cubby Compressors has had relatively steady sales volume for years. The introduction of a new high-end

Question:

14. Cubby Compressors has had relatively steady sales volume for years.

The introduction of a new high-end “biscuit” model for the professional contractor market has added the potential for additional sales. The operations manager is also concerned about losing sales if product is not readily available. The current sales and operations plan is given below.

Assume that each employee can make one unit each work day. Also, assume all days-of-supply calculations are based on a 20-day month and that back orders are to be filled from current production.

a. Propose a revised production plan that brings the days of supply to the target of five days for the next six months.

b. What would the plan look like if you had a hiring freeze at 45 employees maximum and still want to achieve the target five days of supply?

c. What other options are available to not exceed the 45-employee limit and still not experience inventory shortages and related customer service problems?

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: