14. The XYZ Company uses MRP to plan and schedule plant operations. The plant operates five days...
Question:
14. The XYZ Company uses MRP to plan and schedule plant operations.
The plant operates five days per week with no overtime, and all orders are due at 8 a.m. Monday of the week required. It is now 8 a.m.
Monday of week 1, all machines are currently idle, and the production manager has been given the information in Exhibit B.
a. Assuming that the shortest operation next rule is used to schedule orders in the shop, how should the open orders (scheduled receipts)
for items A, B, and C be sequenced at their current operations? What are the implications of this schedule?
b. Assuming that the critical ratio rule is used to schedule orders in the shop, how should the open orders for items A, B, and C be sequenced at their current operations? What are the implications of this schedule?
c. Suppose that 32 additional units of item B have just been found in the stockroom as a result of a cycle count. What actions are required on the part of the MRP planner?
Step by Step Answer:
Manufacturing Planning And Control For Supply Chain Management The CPIM Reference
ISBN: 9781265138516
3rd Edition
Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann