18. The final assembly schedule (FAS) represents which of the following?
I. The assembly plan when a planning bill of fire is used II. The exact set of end products to be built in an assemble-to-order environment III. The plan for moving pre-fabricated components into completed products
a. I only
b. II only
c. III only
d. I, II, and III