2. A final assembly (A) requires one week to assemble and has a component part (B) requiring...
Question:
2. A final assembly (A) requires one week to assemble and has a component part (B) requiring two weeks to fabricate. Three units of final assembly A and four units of part B are currently on hand.
The gross requirements for assembly A for the next 10 weeks are as follows (one part B is used on each A):
Week 1 2 3 4 5 6 7 8 9 10 Requirements 1 4 2 8 1 0 6 2 1 3
a. What are the planned order releases for part B using lot-for-lot lot sizing for both parts A and B?