2. (**) Reconsider the project outlined in Problem 1. Management would like to complete the project in
Question:
2. (**) Reconsider the project outlined in Problem 1.
Management would like to complete the project in less than 12 days. They have determined that Activity C can be crashed four days for a total cost of $10,000. No other activities can be crashed. Will crashing Activity C meet management’s goal of less than 12 days? Why or why not?