21. In a system where timing of production is uncertain, it would be more appropriate to utilize...

Question:

21. In a system where timing of production is uncertain, it would be more appropriate to utilize

a. Safety stock

b. Safety lead time

c. Either would perform adequately

d. Neither would be appropriate