3. Material requirements planning (MRP) systems perform which of these functions? I. Translating the overall production plan
Question:
3. Material requirements planning (MRP) systems perform which of these functions?
I. Translating the overall production plan into detailed steps II. Providing information for capacity planning III. Providing information for staffing plans
a. I only
b. I and II only
c. I and III only
d. I, II, and III