6. A furniture manufacturer makes a bookcase from two end panels, four shelves, fasteners, and hangers. The

Question:

6. A furniture manufacturer makes a bookcase from two end panels, four shelves, fasteners, and hangers. The end panels and shelves have the following data:

image text in transcribed

The master schedule for the next three weeks is 35, 50, and 40 bookcases, respectively. Each MPS quantity requires a setup.

a. What is the total number of hours required on each of the five machine centers for each week?

b. If each of the two parts is started into production one week (five days)
before needed in assembly, and it takes one day per operation, generate the week-by-week load on the routing machine.

c. If, in part

b, the two parts arrive at the router on the same day, which should be processed first? Why?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: