=+6. (*) Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are
Question:
=+6. (*) Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown.
WEEK 1 2 3 4 5 6
***A2*** Gross requirements 200 200 200 300 300 300 LT (weeks) = 2 Scheduled receipts 200 Projected ending inventory: 260 Net requirements Min. order = 1 Planned receipts Planned orders