6. Which of the following are true?

I. The sales and operations planning plan is usually stated in aggregate units.

II. The master production schedule is usually stated in end product units.

III. The sales and operations planning plan and the master production schedule should be stated in the same units.

a. I only

b. II only

c. III only

d. I and II only