9. (**) Reconsider Problem 7 (prior to any changes in Problem 8).Management has determined that the project

Question:

9. (**) Reconsider Problem 7 (prior to any changes in Problem 8).Management has determined that the project must be completed in 25 weeks or less, and that “cost is no object.” How many paths will need to be crashed in order to meet this goal? Which activities do not need to be considered for crashing?