9. (*) The lead time for KraftyCity workbenches is 3 weeks, with a standard deviation of 1.2...
Question:
9. (*) The lead time for KraftyCity workbenches is 3 weeks, with a standard deviation of 1.2 weeks, and average weekly demand is 24, with a standard deviation of 8 workbenches. What should the reorder point be if KraftyCity wants to provide a 95% percent service level?